AQL carried out a restoration and protection measures, including: Surface Preparation: All surfaces within the bund were mechanically prepped, followed by dust and debris removal to allow for a good bonding surface Concrete Repairs- Due to a severe chemical spill, a large hole had formed in the concrete. The area was prepped, rebar treated and a chemical resistant resin solution was used to fix the area. All blowholes or imperfections were also filled using an epoxy filler system. Application of Primer- A quick-curing epoxy primer was applied to the concrete to enhance bonding of the final coatings. Chemical Resistant Coating Application: Chemical resistant coating was applied to specific chemical storage concentrate to protect all concrete surfaces.