client objectives
Ensure the longevity and structural integrity of the water reservoir.
Prevent any water ingress or egress
Ensure compliance with potable water safety standards for internal surfaces.
Prevent water from ponding in the roof drainage system

Scope of works
Surface Preparation Works – All external and internal surfaces were subjected to a high-pressure clean-down to remove contaminants, debris, and surface deterioration. Crack Injection- Crack Injection took place at the wall to floor joint to stop water egress. Roof Joint Filling- All roof joint filler was removed, joints were prepped and new movement mastic was installed to stop any water ingress Screed- A Screed was installed in the roof drainage system, which was part of the concrete roof slab, to form a fall allowing effective drainage. Internal Joints- All internal joints were removed, solid filled and a movement bandage system was install to floor, walls and wall to floor joints.